Ibeju-Epe highway project to be ready in 2022, Sanwo-Olu assures

Governor Babajide Sanwo-Olu of Lagos state has assured residents that the ongoing construction of 18.7-kilometre six-lane rigid pavement carriageway from Eleko Junction in Ibeju Lekki to Epe T-junction would be completed and commissioned in the first quarter of 2022.

Sanwo-Olu, who was excited by the pace of work on the road when he visited the site, persuaded the contractor handling the project to increase its momentum in order to push the progress to an encouraging level before the end of the year.

The governor flagged off the first phase of the expansion on the Lekki-Epe Expressway last November, kick-starting the rehabilitation of the 40-year-old infrastructure. The second phase of the project, which will start later this year, stretches 26.7Km from Eleko Junction to Abraham Adesanya Junction in Eti-Osa axis.

At the time of the governor’s inspection, the contractor had completed a stretch of 3km on the lane from Eleko Junction inward Epe, while the right-of-way for the entire project had been fully cleared.

After communicating the work progress to the governor, representatives of the contractor led Sanwo-Olu and cabinet members on legwork for assessment of features on the completed stretch, including drainage channels, kerb and segregated lane for heavy-duty vehicles.

The Governor was optimistic the project would be delivered on record time, charging the contractor to scale up the pace of work.

He said: “This exercise is an on-the-spot assessment to view the status of the 18.7Km six-lane rigid pavement road construction we are doing from Eleko Junction to Epe. The contractor has been active on site in the last six months, and they have touched every part of the entire stretch.

“We are currently assessing the project from the 3km lane already completed. On either side are three lanes. Two lanes are for cars, while the last lane is for heavy-duty vehicles. There will be a 1.5km pedestrian walkway on both sides.”