Lagos-Ibadan expressway: Kara bridge section opens

The federal government on Sunday opened the Kara Bridge section of the Lagos-Ibadan Expressway to traffic, after completing repair works on a 600-metre stretch, the News Agency of Nigeria (NAN) reports.

NAN reports that the section between Kara Bridge and Isheri Junction inbound Lagos were partially closed on September 2, for reconstruction, resulting in traffic diversion.

When a NAN correspondent visited the site, traffic regulatory agencies, law enforcement agencies and officials of Federal Ministry of Works, Power and Housing officials were supervising removal of barricades by construction workers.

Federal Road Safety Corps (FRSC) personnel closed the Kara end of the bridge, using patrol vehicles to lead vehicles into the newly-constructed lane.

The FRSC in a slow motorcade took off from the Kara end of the bridge at exactly 10:30a.m., leading the vehicles on the Lagos-bound carriageway to merge onto the Lagos traffic at the Isheri intersection on the highway.

An FRSC Assistant Corps Commander, Taofik Iyanda, expressed satisfaction at the road repair, and thanked the Federal Government and its agencies that effected the repairs.

Iyanda appealed to road users to exercise caution while driving on the highway.

“Motorists should not see the road as a race-course. They should exercise patience on the small segment that has been completed and opened for use.

“They should not exceed the specified speed limit.

“The road is still under construction and a lot of things will have to be put in place, so they have to be very careful and exercise patience anytime they are plying the road,’’ he advised.

He told journalists that collaboration of traffic management agencies and law enforcement agencies helped to minimise road accidents and deaths during the repair period.

The Federal Controller of Works in Lagos, Mr Adedamola Kuti, had in an interview with NAN, appealed to road users to observe speed limits to avert crashes.

Kuti, while inspecting the Lagos-Ibadan Expressway on Saturday evening, told NAN that the site cleaning was being completed to prepare for opening of the road to traffic.

“We have already completed the work up to the asphalt level on this inbound Lagos lane.

“We have completed this lane of 600 metres. We were slowed down by that huge October rain.

Leave a Reply